The write-up
Summary
Dan called to report that when the back wall was opened up, the existing lintel over the old door turned out not to be strong enough for the new opening, so building control will require a steel. The steel, padstones and engineer's calculation come to £850 all in, and because the steel has a week's lead time the extension start moves from this Monday to Monday the seventh. You agreed the £850 and asked him to put it in writing. Dan said he can still do the drainage and footings on Thursday and Friday so the week isn't lost, and he'll book the building control inspection for when the steel goes in — you don't need to do anything.
Key points
- Back wall opened up; existing lintel over the old door can't take the new opening
- Building control will require a steel lintel
- Steel, padstones and engineer's calc: £850 all in
- Steel has a one-week lead time
- Drainage and footings can still go ahead Thursday and Friday
- Dan will handle the building control inspection booking
Decisions
- Accept the £850 additional cost for the steel, padstones and engineer's calc
- Proceed with drainage and footings on Thursday and Friday
- Extension start pushed from this Monday to Monday the seventh
Action items
Send the revised quote by WhatsApp
Send the engineer's drawing when it is available
Book the building control inspection for when the steel goes in
Carry out drainage and footings
Promises
WhatsApp the revised quote
Send the engineer's drawing
Book the building control inspection for the steel installation
A follow-up you could send
Hi Dan, thanks for the call. Confirming I'm happy with the £850 for the steel, padstones and engineer's calc, and with starting the extension on Monday the 7th while you do the drainage and footings this Thursday and Friday. Look forward to the revised quote tonight. Cheers.